Church Street, Eccles - Topped out

  • Silverlane Developments
  • Feb 13, 2024
  • 1 min read

A huge milestone for our flagship development in Eccles was completed recently by the topping out of Church Street. The screens are off and the crane is down. We look forward to starting the next stage of this amazing development. Congratulations to all those involved!



Progress from January 2024 (progress week 81).


The progression of the work has been positive and progressing extremely well and slightly ahead of our master on programme. During this period ,progress has continued on the concrete frame tower. In addition, we have got the superstructure to level 22. The Steel Framing System (SFS) and window installation has continued in line with our expectations up to level 20, brickwork is ongoing and is currently up to level 5.


The internal fit out works have also progressed, and we have just completed the 1st fix works up to level 6 and final fix works, Kitchens, Bathrooms, Tiling, decoration and floor finishes are underway from level 1. Roofing works continue to roof areas and terraces.

We are expecting to be topping out on the superstructure frame in March 2024 



 
 
 

Comments


Contact Silverlane

For further information about Silverlane Developments, please call us, email us or complete our enquiry form.

Silverlane Developments
(Registered Office)
Capital House, 272 Manchester Road, Droylsden, Manchester, M43 6PW

E: enquiries@silverlanedevelopments.co.uk
  • LinkedIn

Thanks for submitting!

Silverlance_icon_white.png
Silverlane Developments
(Registered Office)
Capital House 
272 Manchester Road
Droylsden
Manchester
M43 6PW
For enquiries, please email;
enquiries@silverlanedevelopments.co.uk
  • LinkedIn

© 2025 Silverlane Developments.

All rights reserved.

Privacy Policy.

Design: COAST.

bottom of page